Instructions for AmerenUE Permit Application
|
|
Prior to the installation or construction of any activity on or affecting project lands, a permit application must be submitted to AmerenUE. Any activity (except boat docks) located lakeward of elevation 658.5' or in a wetland also requires approval from the Corps of Engineers. Review our Permit Requirements for more information.
|
A completed Permit Application packet must contain the following information.
|
1.
|
Application for an AmerenUE Permit—Include name, address and a detailed description of the proposed project and its location.
|
2.
|
Specification Sheet (Docks Only).
|
3.
|
Drawings to scale on 8 1/2 " x 11" paper.
Drawings must show the following information:
|
|
|
All Activities:
|
|
|

|
General vicinity map showing the property in relation to the nearest lake mile.
|
|
|

|
Location of the activity within the applicant’s property lines extended lakeward.
|
|
|
Dock (Drawing 1-1):
|
|
|

|
Drawing showing the location of the dock in relation to docks on either side and across the cove or channel from the applicant’s dock.
|
|
|

|
Distance from the dock to the applicant’s property lines extended lakeward.
|
|
|

|
Distance from the end of the dock to the center of the channel or cove and the distance across the channel or cove.
|
|
|

|
Distance to the nearest dock on each side of applicant’s dock.
|
|
|

|
Dimensions of the proposed dock.
|
|
|

|
The dock location drawing must be drawn to scale.
|
|
|
Bank Stabilization (Drawing 1-2):
|
|
|

|
Lowest elevation of the proposed activity. For a concrete seawall, this would generally be the elevation at the base of the wall.
|
|
|

|
Distance from the toe of the bank to the seawall.
|
Use our convenient checklist to make sure you have not left anything out. Then, mail the completed application packet to:
|
|
|
AmerenUE
P.O. Box 993
Lake Ozark, Missouri 65049
|
|
|
|
View our Permit Procedures for more information.
|