Checklist
Print this checklist to make sure you have not left anything out of your Permit Application.
|
|
|
Your application packet should include:
|
|
|

|
Signed Application for AmerenUE permit
|

|
Specification sheet
|

|
A summary of the proposed use’s expected impact on the environment and compliance with AmerenUE guidelines
|

|
For proposed uses that will require FERC review and approval (See Table 5 in the SMP), an explanation of compatibility with Commission-approved management plans, project operations and purposes, applicable license requirements, as well as Application for an AmerenUE Permit
|

|
Drawings to scale (on 11”x17” max. paper) showing all measurements and elevations as specified on Application for an AmerenUE Permit
|

|
Breakwaters and docks with more than 4 slips, registered engineer drawing
|

|
Processing Fee (according to the Fee Schedule)
|

|
Use Fee must be submitted with application. If the dock is subject to an annual use fee, do not send it with the application.
|
|
|
|
Send your application packet to:
|
|
|
AmerenUE
P.O. Box 993
Lake Ozark, MO 65049
|
|
|
|
After your application packet is received, AmerenUE will:
- Review the application.
- Request any necessary approvals from federal, state or local agencies.
- Approve the application as submitted, approve the application with conditions or deny the application.
|