Milestones
|
|
|
|
|
Date
|
|
|
Milestone
|
|
July 16, 1973
|
- Project announced and site selected
|
|
April 1, 1975
|
- Certificate of Convenience and Need granted by the Missouri Public Service Commission
|
|
August 14, 1975
|
- Limited Work Authorization granted by the U.S. Nuclear Regulatory Commission (NRC)
|
|
|
|
April 16, 1976
|
- Construction permit granted by the NRC
|
|
|
|
October 19, 1979
|
- Application made to the NRC for the plant’s operating permit
|
|
|
|
November 16, 1982
|
|
|
|
|
June 11, 1984
|
- “Low power” operating license issued by the NRC
|
|
|
|
June 13, 1984
|
|
|
|
|
October 2, 1984
|
- First nuclear chain reaction took place
|
|
|
|
October 18, 1984
|
- “Full power” operating license issued by the NRC
|
|
|
|
December 19, 1984
|
- Required testing completed
- Plant declared fully operational
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|