Application Process for Your Solar Project

 

Application Process for a Solar Project

Please refer to Net Metering Application/Agreement and the Net Metering Requirements Checklist when completing the application steps. View the complete Net Metering Tariff (which includes prices for excess energy) if your system is below 100 kW. View the complete Qualifying Facilities Tariff.

Ameren Missouri reviews the interconnection application system designs and replies to the customer within 30 days (10 kilowatt (kW) and below systems) or 90 days (11 kW - 100 kW systems).

If more information is needed, Ameren Missouri contacts the installer via email to request specific information.  The 30 or 90 days to reply does not begin until all information is received.

When the system is approved, Ameren Missouri will email the customer and installer a design approval letter that approves the customer to proceed with system installation.


Apply Online for your Interconnection Application or Solar Rebates

apply now


Email

Solar@ameren.com


MAIL original interconnection applications, which includes a one line drawing and spec sheets for the inverter and solar panels, to:

Ameren Missouri Renewables

1900 Chouteau Avenue

MC 1450

St. Louis, MO 63103



MAIL original interconnection applications which includes a one line drawing and spec sheets for the inverter and solar panels to:
MAIL original interconnection applications which includes a one line drawing and spec sheets for the inverter and solar panels to: