The regional grid operator, Midcontinent Independent System Operator (MISO), identified the need for this project to support new, third-party energy sources. As the incumbent energy provider, federal regulation requires Ameren Missouri to develop grid infrastructure projects that fulfill these needs.
Increased Capacity
Reliability
Energy Sources
Development Opportunities
Fall 2024 – Early 2025
Early 2025 – Fall 2025
Fall 2025
Fall 2025 – Spring 2027
Spring 2027 – Spring 2028
Fall 2027 – Spring 2029
Summer 2029 – 2030
Late 2030
Following a detailed routing study and feedback from residents, agencies and officials gathered at multiple open houses and online, a Proposed Route has been selected and filed with the Missouri Public Service Commission (PSC). Thank you to everyone who participated and provided input during our engagement process.
On Nov. 10, 2025, Ameren Missouri submitted an application to the MO PSC for a Certificate of Convenience and Necessity (CCN) for the Montgomery-Callaway Connector Project. Routes are not final and are subject to final approval by the PSC. The expected timing for the PSC's decision is fall 2026.
If approved by the PSC, easement negotiations will begin with affected landowners shortly after. Vegetation clearing and pre-construction activities are planned to begin in 2027. The goal is to have this new project in service and providing benefits to the local community by the end of 2030. Our project team will maintain ongoing communications with landowners, local government, agencies and other stakeholders during the project.