The Southern Illinois Reliability Project reconstructed the existing 230-kV transmission line from Cahokia to Joppa, originally built in the 1950s. Customers in St. Clair, Washington, Perry, Franklin, Williamson, Johnson, and Massac counties are now benefiting from the infrastructure upgrades.
The upgraded transmission line is improving system reliability while opening pathways for clean energy to be distributed to the region. It is also increasing transmission capacity to meet the area's growth needs. Crews completed the Southern Illinois Reliability Project in December 2023. Land restoration efforts were completed in the spring of 2024.
Completion Date: December 2023
Type: 340-kV transmission line
Length: 140 miles across 7 counties
Reliability
Renewable Energy
Capacity
Phone: 618.808.3093
Email: SouthernILReliability@ameren.com
Mail: Southern Illinois Reliability Project c/o Volkert, 1500 Eastport Plaza Drive, Suite 200, Collinsville, IL 62034