Crossroads Connector Project
Ameren Missouri is working to build a more reliable and resilient energy grid. The Crossroads Connector Project includes the construction of a new substation named Float and approximately 22 miles of new double circuit, 345 kilovolt (kV) transmission lines developed in two phases in Montgomery and Warren Counties. The Project will increase transmission capacity to meet the anticipated energy demand from new economic development in the area and strengthen the grid for all customers.
Project Details

Missouri has one of the strictest laws in the nation, Missouri Senate Bill 4, requiring data centers to pay for the costs to serve them while providing robust protection for all other customers. Ameren Missouri’s Powering Missouri Growth Plan, in alignment with Missouri Senate Bill 4, requires new large load businesses to pay upfront 100% of direct interconnection costs and upfront financial security and collateral requirements equivalent to two years of minimum monthly bills, and Ameren Missouri will ask state regulators to ensure that the rates paid by nearby data centers fully cover the costs of the entire project in a future regulatory filing.

Phase 1 of the project includes constructing approximately 4 miles of new 345 kV double circuit transmission line to connect the new Lumberjack substation southeast of New Florence to the existing Montgomery-Callaway 345 kV transmission line located west of New Florence.

Phase 2 of the project includes constructing approximately 18 miles of new 345 kV double circuit transmission line and a new substation named Float west of Warrenton. The new line will connect the Float substation to the new Nightingale and Lumberjack substations located east and southeast of New Florence.

Project Benefits
Increasing transmission capacity to meet growing energy demand
Improving energy reliability for the surrounding area
The purpose of our public engagement is for stakeholders, agencies and landowners to learn about the Project, discuss their questions and concerns with our Project team, and provide input on sensitivities and opportunities. We appreciate your participation, as it helps us understand the Project Area from your perspective. We plan to host open houses in late October 2026.
2026 2027 2028
  • Gather public, stakeholder and agency input
  • Route siting studies
  • Routes identified
  • Easement acquisition
  • Environmental surveys, engineering and permitting
  • Pre-construction activities
  • Phase 1 construction begins
  • Phase 2 construction begins
  • Line construction
  • Float substation completion
  • Phase 1 in service
  • Phase 2 in service
  • Restoration (Through Spring 2029)
Scroll, zoom and search your address on the interactive map. Having trouble viewing the interactive map? This map works best in updated versions of Microsoft Edge and in Google Chrome or Firefox.
Meeting Format Date Time Address
In-Person Morning Session in Truesdale* Thursday, October 22, 2026 11:00 a.m.-1:00 p.m. The Mary Lou Community Center
821 Market St., Truesdale, MO 63380
In-Person Afternoon Session in Jonesburg* Thursday, October 22, 2026 5:00 p.m.-7:00 p.m. Jonesburg Community Building
111 N 1st St., Jonesburg, MO 63351
Virtual Open House View the Virtual Open House (PDF)
*Both open house meeting sessions will feature the same project information and are being offered at different times to accommodate varying schedules. The open house will be held in a come-and-go format with no formal presentation. Project team members will be available throughout the event to provide information, answer questions, and gather feedback.
Contact Us

Phone: 573.367.5246

Email: connect@crossroadsconnectorproject.com

Mail: Crossroads Connector Project, Attn: WSP 701 Emerson Road, Suite 250 Creve Coeur, MO 63141

Frequently Asked Questions