Eastern Missouri Grid Transformation Project
Ameren Transmission Company of Illinois (ATXI) and Ameren Missouri are working together to build a more reliable and resilient energy grid for the future. 
About the Project

The Eastern Missouri Grid Transformation Project includes more than 130 miles of new and upgraded transmission lines through Marion, Ralls, Pike, Lincoln, St. Charles and St. Louis counties, as well as the City of St. Louis. 

The vast majority of the lines will be rebuilt along existing corridors and co-located with existing Ameren facilities. This project will prepare the grid for the future by replacing aging infrastructure, adding transmission capacity to ensure reliability and resiliency, and promoting more access to a balanced mix of energy sources for communities. A virtual Comment Form is available on the Interactive Map to share your feedback and sign up for the mailing list.

Community Benefits
Increasing transmission capacity to meet changing energy needs
Supporting stable energy prices
Improving energy reliability for the surrounding region and local communities
Promoting access to a balanced mix of energy sources
Growing economic development opportunities
Project Overview

 

Anticipated Schedule

Summer Through Fall 2025 Winter Through Spring 2026 Spring Through Summer 2026 Summer 2026 Through 2028
  • Project planning and initial stakeholder engagement
  • Routing and public engagement
  • Finalize route
  • File final route with the Missouri Public Service Commission
  • Real estate begins
  • Receive a Certificate of Convenience and Necessity (CCN) from the Missouri Public Service Commission
  • Permitting and agency coordination
  • Environmental studies/surveys
2028 - 2032 2032 2033
  • Construction (different start dates in each community)
  • Construction complete
  • Project in service
  • Land restoration complete

*All items shown are pending regulatory approvals. Schedule is subject to change.

 

Public Outreach & Stakeholder Involvement

Community leaders and members of the public will have various opportunities to provide input during each phase of the routing process as the preferred route is defined and submitted in an application for a certificate to the Missouri Public Service Commission later this year. The goal of the routing process is to identify and take advantage of opportunities while understanding and minimizing impacts to sensitivities while adhering to technical guidelines and statutory requirements.

The team will gather and review data from community members, landowners, and stakeholders during different stages of the routing process. Public outreach and stakeholder engagement will take place through a series of open houses in March 2026 to gather input on the route segments. All input received during the outreach and engagement process will be reviewed and considered, along with project routing criteria during the development of the Proposed Route.

Public collaboration remains a top priority for the project team, and community participation throughout the public engagement process is deeply appreciated. Please stay involved in the process by joining the project email and/or mailing list  to receive updates on the project in your county.

 

Open Houses

Meeting Format Date Time Address
In-Person
Marion County
Monday, March 2 11 a.m. - 1 p.m. and 5 - 7 p.m. Iron Gate Estate
4603 US Highway 61
Palmyra, MO 63461
In-Person
Ralls County
Tuesday, March 3 11 a.m. - 1 p.m. and 5 - 7 p.m. New London Lions Club
600 West Street
New London, MO 63459
In-Person
Pike County
Wednesday, March 4 11 a.m. - 1 p.m. and 5 - 7 p.m. VFW Post 5553
505 VFW Road
Bowling Green, MO 63334
In-Person
Lincoln County
Thursday, March 5 11 a.m. - 1 p.m. and 5 - 7 p.m. Knights of Columbus Hall
500 Highway J
Troy, MO 63379
In-Person
St. Charles County
Monday, March 9 11 a.m. - 1 p.m. and 5 - 7 p.m. Kohl-Jeck VFW Post 2866
66 VFW Lane
St. Charles, MO 63303
In-Person
St. Charles County
Tuesday, March 10 11 a.m. - 1 p.m. and 5 - 7 p.m. O’Day Lodge
1100 O’Day Park Drive
O'Fallon, MO 63368
In-Person
St. Louis County
Wednesday, March 11 11 a.m. - 1 p.m. and 5 - 7 p.m. VFW Post 3944
10817 Midland Blvd.
Overland, MO 63114
In-Person
City of St. Louis
Thursday, March 12 11 a.m. - 1 p.m. and 5 - 7 p.m. O'Fallon Park Rec Complex YMCA
4343 W Florissant Ave
St. Louis, MO 63115
Virtual Open House Begins
​
March 2
Ongoing
Virtual Open House (PDF)
The Project in Marion County

The Project consists of five (5) line segments, including the Maywood-Belleau line segment within Marion County. This segment upgrades the transmission line from the existing Maywood substation near Palmyra to the existing Belleau substation in O'Fallon. Specifically in Marion County, the Project involves:

  • Replacement  – Replacing 18 miles of existing wood H-frame structures with new steel monopoles to carry additional energy. In most instances, the number of structures is lessened with a smaller footprint due to design and longer spans. New structures will typically be constructed within existing corridors.
  • New Corridor  – Up to 2 miles of the new transmission line may be re-routed in a new corridor through the county. The new structures may be constructed as double circuit with the existing 161 kV circuits being relocated along a new transmission corridor. 
The Project in Ralls County

The Project consists of five (5) line segments, including the Maywood-Belleau line segment within Ralls County. This segment upgrades the transmission line from the existing Maywood substation near Palmyra to the existing Belleau substation in O'Fallon. Specifically in Ralls County, the Project involves:

  • Replacement – Replacing 16 miles of existing wood and steel H-frame structures with new steel monopoles to carry additional energy. In most instances, the number of structures is lessened with a smaller footprint due to design and longer spans. New structures will typically be constructed within existing corridors.
  • New Corridor  – Up to 4 miles of the new transmission line may be re-routed along a new corridor through the county.
The Project in Pike County

The Project consists of five (5) line segments, including the Maywood-Belleau line segment within Pike County. This segment upgrades the transmission line from the existing Maywood substation near Palmyra to the existing Belleau substation in O'Fallon. Specifically in Pike County, the Project involves:

  • Replacement – Replacing 27 miles of existing wood H-frame structures with new steel monopoles to carry additional energy. In most instances, the number of structures is lessened with a smaller footprint due to design and longer spans. New structures will typically be constructed within existing corridors. 
  • New Corridor  – Up to 11 miles of the new transmission line may be re-routed in new corridors through the county. The new structures may be constructed as double circuit with the existing 161 kV circuits being relocated along a new transmission corridor. 
The Project in Lincoln County

The Project consists of five (5) line segments, including the Maywood-Belleau line segment within Lincoln County. This segment upgrades the transmission line from the existing Maywood substation near Palmyra to the existing Belleau substation in O'Fallon. Specifically in Lincoln County, the Project involves:

  • Replacement – Replacing 27 miles of existing wood H-frame structures with new steel monopoles to carry additional energy. In most instances, the number of structures is lessened with a smaller footprint due to design and longer spans. New structures will typically be constructed within existing corridors. 
  • New Corridor  – Up to 9 miles of new transmission line may be routed along new corridors through the county. 
The Project in St. Charles County

The Project consists of five (5) segments, including the Maywood-Belleau, Belleau-Graus, Graus-Sioux, and Graus-Bugle segments within St. Charles County. These segments upgrade the transmission line, and specifically in St. Charles County, the Project involves:

  • Replacement – Replacing 35 miles of existing wood and steel H-frame structures and lattice towers with new steel monopoles to carry additional energy. In most instances, the number of structures is lessened with a smaller footprint due to design and longer spans. New structures will typically be constructed within existing corridors.
  • New Corridor  – Up to 19 miles of new transmission line may be re-routed in new corridors through the county. 
  • New Substation  – A new 345 kV substation called Graus will be constructed.
The Project in St. Louis County and the City of St. Louis

The Project consists of five (5) segments, including the Graus-Bugle and Bugle-Mississippi River Crossing segments within St. Louis County and the City of St. Louis. These segments upgrade the transmission line, and specifically in St. Louis County and the City of St. Louis, the Project involves: 

  • St. Louis County Replacement – Replacing 16 miles of existing steel monopoles and lattice towers with new steel monopoles to carry additional energy. In most instances, the number of structures is lessened with a smaller footprint due to design and longer spans. New structures will typically be constructed within existing corridors. A short section of transmission line near Bugle Substation may be routed in a new corridor outside of existing right-of-way. 
  • City of St. Louis Replacement  – Replacing 10 miles of existing steel monopoles and lattice towers with new steel monopoles to carry additional energy. In most instances, the number of structures is lessened with a smaller footprint due to design and longer spans. New structures will typically be constructed within existing corridors. Up to 2 miles of new transmission may be re-routed along a new corridor outside of existing right-of-way. 
General Information
Engagement
Environmental & Agency Coordination
Contact Us

Phone: 877.468.1823

Email: Connect@EasternMOGrid.com

Mail: Eastern Missouri Grid Transformation Project Attn: WSP, 701 Emerson Road, Suite 250, Creve Coeur, MO 63141Â